Hello

Is Microsoft Project 2003 having capability of Bug Tracking, Employee
attendance? Or Microsoft or any third party these tool which can easily
integrate with MS Project 2003 prefreable web based platform?
Steve House [MVP]
2004-12-31 14:10:30 UTC
Permalink
MS Project is fundamentally a project work planning tool. It really doesn't
have any ability to track bugs or attendance. If you are using Project
Server you might be able to adapt its issues tracking tools for bug tracking
but aside from that, there really isn't anything I'm aware of.
--
Steve House [MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs
Post by Ashish Kanoongo
Hello
Is Microsoft Project 2003 having capability of Bug Tracking, Employee
attendance? Or Microsoft or any third party these tool which can easily
integrate with MS Project 2003 prefreable web based platform?
Rob Schneider
2005-01-01 11:23:11 UTC
Permalink
See http://www.gamasutra.com/features/20031120/hansen_02.shtml where a
development company wrote up an article on how they integrated Bugzilla
(open source bug tracking system from Mozilla) and Microsoft Project.
Post by Steve House [MVP]
MS Project is fundamentally a project work planning tool. It really
doesn't have any ability to track bugs or attendance. If you are using
Project Server you might be able to adapt its issues tracking tools for
bug tracking but aside from that, there really isn't anything I'm aware of.
Steve House [MVP]
2005-01-02 12:22:34 UTC
Permalink
Thanks - I'll look it up
--
Steve House [MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs
Post by Rob Schneider
See http://www.gamasutra.com/features/20031120/hansen_02.shtml where a
development company wrote up an article on how they integrated Bugzilla
(open source bug tracking system from Mozilla) and Microsoft Project.
Post by Steve House [MVP]
MS Project is fundamentally a project work planning tool. It really
doesn't have any ability to track bugs or attendance. If you are using
Project Server you might be able to adapt its issues tracking tools for
bug tracking but aside from that, there really isn't anything I'm aware of.
Loading...