is PPC - eg.: scheduling, rescheduling, job tracking, daily production
entry, attendance, production shortfall, etc....

running a small machining/manufacting workshop application developed on
MS Project platform.

Kamal
Jan De Messemaeker
2005-04-21 15:55:32 UTC
Permalink
Hi Kamal,

You're running it, so youknow SOME of it is feasible.
What exactly are your doubts?

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/
+32-495-300 620
Post by freedom
is PPC - eg.: scheduling, rescheduling, job tracking, daily production
entry, attendance, production shortfall, etc....
running a small machining/manufacting workshop application developed on
MS Project platform.
Kamal
freedom
2005-04-25 17:31:21 UTC
Permalink
I am a manufacturer for OE supplies


daily data entry...
like my daily part production in the different operations & stages.

to be clear...
operation
planned xxx processed yyy
first operation is part cuttung from bars>
planned 550 prcossed 480

second operation is making holes in that part. >
planned 250 processed 50

third operation is painting >
planned 5kgs processed 10kgs

hope you get the picture time required changes as per the schedule for
the said month. my working is on a montly basis(recurring) OR lot size
basis(three to seven times a year).

I have been going through the program but it looks project 2000 wont
work for me.
Jan De Messemaeker
2005-04-25 17:42:35 UTC
Permalink
Hi freedom,

I think I could find ways and means to solve most of your problems but it
would still be only just.
Especially for recurrent productions, Project is too much
"project"-oriented.
IMHO a valuable tool for unique batches (because simpler and cheaper that
the production SW I saw) but for recurrent... I hesitate.
HTH

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/
+32-495-300 620
Post by freedom
I am a manufacturer for OE supplies
daily data entry...
like my daily part production in the different operations & stages.
to be clear...
operation
planned xxx processed yyy
first operation is part cuttung from bars>
planned 550 prcossed 480
second operation is making holes in that part. >
planned 250 processed 50
third operation is painting >
planned 5kgs processed 10kgs
hope you get the picture time required changes as per the schedule for
the said month. my working is on a montly basis(recurring) OR lot size
basis(three to seven times a year).
I have been going through the program but it looks project 2000 wont
work for me.
Rod Gill
2005-04-25 21:49:28 UTC
Permalink
I agree with Jack: Microsoft Project is not production software. You will
need careful, skilled use of Project to get what you want. The moment an
unskilled person tries to update it you will get chaos. Production software
is going to cost more, but should add more value.

See if there's a production add-on for your accountancy software.
--
Rod Gill
Project MVP
Post by Jan De Messemaeker
Hi freedom,
I think I could find ways and means to solve most of your problems but it
would still be only just.
Especially for recurrent productions, Project is too much
"project"-oriented.
IMHO a valuable tool for unique batches (because simpler and cheaper that
the production SW I saw) but for recurrent... I hesitate.
HTH
--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/
+32-495-300 620
Post by freedom
I am a manufacturer for OE supplies
daily data entry...
like my daily part production in the different operations & stages.
to be clear...
operation
planned xxx processed yyy
first operation is part cuttung from bars>
planned 550 prcossed 480
second operation is making holes in that part. >
planned 250 processed 50
third operation is painting >
planned 5kgs processed 10kgs
hope you get the picture time required changes as per the schedule for
the said month. my working is on a montly basis(recurring) OR lot size
basis(three to seven times a year).
I have been going through the program but it looks project 2000 wont
work for me.
freedom
2005-04-26 12:15:42 UTC
Permalink
Can a develop my production software on any of the microsoft platform