Bill Bonds
2003-10-24 13:37:06 UTC
Inserting a new task does not increment predecessors.
In below example, Task10 is a predecessor of Task2.
Clicking Task9 and inserting a new task does not increment
Task2's predecessor to 11, which it should. However,
selecting Task3 and inserting a new task does increment
properly. Also, inserting 2 successive tasks, and then
deleting the second one, causes Project to correctly show
Task11 as Task2's predecessor.
Also, I just noticed, toggling out of and back into
Project forces update. What's going on here?
I'm using Project 2000 on NT4 SP6.
Any help will be greatly appreciated. THANKS!!!
SummaryTask1
Task2
Task3
Task4
Task5
Task6
Task7
SummaryTask8
Task9
Task10
Task11
Task12
Task13
Task14
In below example, Task10 is a predecessor of Task2.
Clicking Task9 and inserting a new task does not increment
Task2's predecessor to 11, which it should. However,
selecting Task3 and inserting a new task does increment
properly. Also, inserting 2 successive tasks, and then
deleting the second one, causes Project to correctly show
Task11 as Task2's predecessor.
Also, I just noticed, toggling out of and back into
Project forces update. What's going on here?
I'm using Project 2000 on NT4 SP6.
Any help will be greatly appreciated. THANKS!!!
SummaryTask1
Task2
Task3
Task4
Task5
Task6
Task7
SummaryTask8
Task9
Task10
Task11
Task12
Task13
Task14