Checking different between the original(base) and actual task timing
(too old to reply)
Teres
2005-09-22 02:26:08 UTC
Permalink
Dear all,

If I want to check the difference between the original(base) task timing
(e.g. starting date, duration, end date) and the actual timing, is there any
pre-built table, view for me to easy follow up?

Thanks in advanced for any advice!

Best reagrds,
Teres Wong
unknown
2005-09-22 03:37:59 UTC
Permalink
Teres --

Yes. You can apply the Tracking Gantt view to visually compare the current
schedule against the baseline schedule. In addtion, you can apply the task
Cost, Work, and Variance tables and study the Variance column in each table.
Click View - Table and then select one of these three tables. Hope this
helps.
--
Dale A. Howard [MVP]
Enterprise Project Trainer/Consultant
http://www.msprojectexperts.com
http://www.projectserverexperts.com
"We wrote the book on Project Server"
Post by Teres
Dear all,
If I want to check the difference between the original(base) task timing
(e.g. starting date, duration, end date) and the actual timing, is there
any pre-built table, view for me to easy follow up?
Thanks in advanced for any advice!
Best reagrds,
Teres Wong