Discussion:
highlight constraint violations
(too old to reply)
l***@yahoo.com
2005-02-01 21:09:18 UTC
Permalink
I have a very large project that I am managing, and occasionally when I
reshuffle dates or predecessors MS-Project warns me that I would be
creating a constraint violation if I continue.

For one particular task, I *do* want to show a constraint violation to
show team members the impact of making a certain decision. I would
like Project to highlight the violation on a Network Diagram or on a
Gantt chart, so when I print it out people can focus on it.

Is there a way MS-Project will automatically highlight constraint
violations?

Thanks!

lc.
Rod Gill
2005-02-02 06:34:11 UTC
Permalink
Hi,

Adding dates (constraints) like this causes all sorts of problems in a
schedule. for example invalid critical paths and the need to manually adjust
schedules rather than use links and have task re-schedule themselves
automatically.

A much better way is to add a Deadline (Project 2000+) to a task by
double-clicking it and looking at the Advanced tab or inserting the Deadline
column. A deadline on a task shows what the task's deadline is and affects
the critical path as well. If a deadline is missed, Project shows a red
diamond in the Indicator column. This will highlight your conflict for you.
--
Rod Gill
Project MVP
Post by l***@yahoo.com
I have a very large project that I am managing, and occasionally when I
reshuffle dates or predecessors MS-Project warns me that I would be
creating a constraint violation if I continue.
For one particular task, I *do* want to show a constraint violation to
show team members the impact of making a certain decision. I would
like Project to highlight the violation on a Network Diagram or on a
Gantt chart, so when I print it out people can focus on it.
Is there a way MS-Project will automatically highlight constraint
violations?
Thanks!
lc.
Jan De Messemaeker
2005-02-02 07:10:34 UTC
Permalink
Hi,

To show the impact of constraint violations on a Gantt Chart (and also the
deadline violations BTW)

In a custom Flag field (say Flag1) set the formula that it is Yes when Total
Slack<0
Then in Bar Styles create an extra line:

Name : Violators (for instance)
Appearance: select an aggressive color like Lime
Show For: select Flag1
From: Start
To: Finish

HTH



--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/index.htm
32-495-300 620
Post by l***@yahoo.com
I have a very large project that I am managing, and occasionally when I
reshuffle dates or predecessors MS-Project warns me that I would be
creating a constraint violation if I continue.
For one particular task, I *do* want to show a constraint violation to
show team members the impact of making a certain decision. I would
like Project to highlight the violation on a Network Diagram or on a
Gantt chart, so when I print it out people can focus on it.
Is there a way MS-Project will automatically highlight constraint
violations?
Thanks!
lc.